Cadeler plc filed a Form 6-K with the SEC on November 12, 2026, announcing that it has signed an exclusivity agreement with an undisclosed client for wind turbine and foundation installation at a large-scale offshore wind farm in the United Kingdom.

Key Highlights

  • Exclusivity agreement signed: Cadeler has entered into an exclusivity agreement with an undisclosed client for a large-scale offshore wind farm in the UK.
  • Installation timeline: The installation campaign is expected to commence around 2030, according to the filing.
  • Multi-vessel deployment: The foundations campaign is to be executed using an A-Class vessel and an O-Class vessel, with wind turbines to be installed by a P-Class vessel.
  • Client identity withheld: The filing does not identify the client, describing it only as "an undisclosed client."
  • CEO statement: CEO Mikkel Gleerup described the project as "another important endorsement of the capabilities of our fleet, the experience of our people and Cadeler's ability to deliver increasingly large and complex offshore wind projects."

Cadeler Secures UK Wind Farm Installation Exclusivity Ahead of 2030 Campaign

Cadeler plc, listed on both the New York Stock Exchange and the Oslo Stock Exchange under the ticker NYSE:CDLR, disclosed the exclusivity agreement in a press release dated November 11, 2026, included in its Form 6-K filing. According to the filing, the agreement covers both foundation installation and wind turbine installation at a UK offshore wind farm described as large-scale, though no project name, location, or contract value was disclosed.

The filing states that the foundations campaign will be carried out using an A-Class vessel and an O-Class vessel, while wind turbine installation will be handled by a P-Class vessel. The installation campaign is expected to begin around 2030. The filing characterizes the agreement as reflecting "the importance of securing installation capacity early in the development of large-scale offshore wind projects," a description attributed to the company's announcement rather than presented as an independent assessment.

CEO Mikkel Gleerup is quoted in the filing commenting on the announcement. No financial terms, contract duration, or specific project capacity figures were included in the disclosure. The filing was signed by Mikkel Gleerup in his capacity as Chief Executive Officer and submitted to the SEC on November 12, 2026, under Commission File Number 333-298599.

What Was Disclosed

Cadeler plc reported the signing of an exclusivity agreement for offshore wind installation work at an unnamed UK project, with work expected to begin around 2030 using three vessel classes. No financial terms or client identity were disclosed.