Companhia Siderúrgica Nacional (National Steel Company) filed a Form 6-K with the SEC on September 29, 2026, disclosing that its subsidiary CSN Mineração S.A. is temporarily reducing lower-grade iron ore production at its Pires Complex dry processing plant and revising its full-year 2026 guidance accordingly.
Key Highlights
- Production cut location: The temporary reduction affects lower-grade iron ore output at the dry processing plant of the Pires Complex in Ouro Preto, Minas Gerais, Brazil.
- Revised volume guidance: The 2026 production and third-party ore purchase volume guidance was lowered from 45.0-47.0 Mt to 39.0-41.0 Mt.
- Revised cost guidance: The 2026 C1 cash cost guidance was raised from US$22.0/ton to US$23.5/ton to a new range of US$25.0/ton to US$26.0/ton.
- Stated driver: The company cited more challenging market conditions, including pressure from higher freight costs, as the basis for the decision.
- Reversibility: According to the filing, the measure may be reversed at any time, with no material impact, should market conditions support stronger margins for this type of ore.
CSN Mineração Reduces Dry-Plant Output Amid Freight Cost Pressure
Companhia Siderúrgica Nacional, listed on NYSE:SID and on Brazil's B3 exchange under the ticker CSNA3, disclosed through its subsidiary CSN Mineração S.A. that it is implementing a temporary reduction in the production of lower-grade iron ore at the dry processing plant of the Pires Complex. The Pires Complex is situated in Ouro Preto, Minas Gerais, a key iron ore producing region in Brazil. The company disclosed the action pursuant to Article 157, Paragraph 4, of Brazilian Law No. 6,404/1976 and CVM Resolution No. 44/2021, characterizing it as a Material Fact for shareholders and the market.
According to the filing, the decision to scale back output at the dry plant reflects "more challenging market conditions, including pressure from higher freight costs." The company noted that the measure reduces both production volumes and the volume of third-party ore purchases expected over the coming months. These combined reductions prompted the downward revision in volume guidance, from the previously disclosed range of 45.0-47.0 Mt to 39.0-41.0 Mt for full-year 2026. At the same time, C1 cash cost guidance was revised upward, moving from the prior range of US$22.0/ton to US$23.5/ton to a new range of US$25.0/ton to US$26.0/ton, reflecting the impact of lower production volumes on unit costs.
The company stated that the revised guidance will be included in Section 3 of its Reference Form, to be made available within the applicable legal deadline on the CVM website and on CSN's Investor Relations website. CSN clarified that "the information disclosed herein constitutes estimates and is subject to market factors beyond the Company's control," and that it "does not constitute a guarantee or promise of performance." The filing also contains forward-looking statements that, according to the company's own cautionary language, are subject to risks, uncertainties, and assumptions that could cause actual results to differ materially from current expectations.
What Was Disclosed
Companhia Siderúrgica Nacional filed a Form 6-K on September 29, 2026, reporting a temporary lower-grade iron ore production cut at CSN Mineração's Pires Complex and revising its 2026 volume and C1 cash cost guidance ranges downward and upward, respectively.