New Era Energy & Digital, Inc. filed a Form 8-K on September 21, 2026, reporting that its subsidiary entered into a Power Purchase Agreement and a Development Framework Agreement on September 18, 2026, securing electricity supply for a planned data center near Odessa, Texas.
Key Highlights
- Power supply secured: Subsidiary TCDC PowerCo LLC agreed with Luminant ET Services Company LLC to receive a minimum of 200 MW and up to 207 MW of electric energy.
- Source facility: Power is to be generated from a 1,180 MW natural gas-fired electric generating facility in Odessa, Texas, owned by Vistra Operations Company LLC.
- 20-year initial term: The agreement commences on the date Luminant first delivers energy, with automatic successive one-year renewal periods unless either party provides written notice of non-renewal.
- Credit support required: New Era must post a letter of credit of $116,000,000 within 15 business days of the PPA date, plus additional security not to exceed $82,800,000 before the delivery date.
- Conditions precedent deadline: Luminant's obligations are subject to certain conditions being satisfied by December 31, 2027, including execution of the Phase 1 Purchase and Sale Agreement for the related substation and equipment.
- Equity interest granted: Under the Development Framework Agreement, New Era will cause the project company to issue Vistra non-voting equity interests representing 5% of its fully diluted equity interests.
- Right of first refusal: The Development Framework Agreement grants Vistra a right of first refusal, beginning in April 2028, on future onsite generation or power build-out opportunities at the Ector County, Texas data center site.
New Era Energy's Power and Development Agreements for the Texas Critical Data Center Project
According to the filing, TCDC PowerCo LLC, a subsidiary of New Era Energy & Digital, Inc. (NASDAQ:NUAI), entered into a Power Purchase Agreement with Luminant ET Services Company LLC on September 18, 2026. Under the PPA, Luminant agreed to supply between 200 MW and 207 MW of electric energy for delivery to the company's Texas Critical Data Center project, which is to be located on property near the Odessa Plant. The company disclosed that power may be sourced from the 1,180 MW natural gas-fired facility owned by Vistra Operations Company LLC, from other available sources, or from the ERCOT grid.
The filing describes significant credit support obligations placed on New Era. The company is required to post a letter of credit in the amount of $116,000,000 within 15 business days of the PPA date. Additional security of up to $82,800,000, in a form mutually agreed upon by both parties, must be posted on or before the delivery date. The filing also notes that if New Era fails to timely execute the Phase 1 Purchase and Sale Agreement and does not pay invoiced Phase 1 construction costs, Luminant's affiliate may draw on New Era's credit support for such costs, up to $116.0 million.
Concurrently, Texas Critical Data Centers LLC, another subsidiary of the company, entered into a Development Framework Agreement and Side Letter to Power Purchase Agreement with Vistra. The DFA grants Vistra a right of first refusal beginning in April 2028 on future data center expansion power opportunities at the Ector County site, as well as a five-year right of first offer on certain electrical power generation and battery storage projects the company proposes to pursue. The DFA also obligates New Era to reimburse Vistra for certain construction costs relating to substations and transmission lines, subject to execution of Purchase and Sale Agreements. The company noted that the full texts of the PPA and DFA will be filed with its Form 10-Q for the quarterly period ending September 30, 2026. The filing contains forward-looking statements, which the company cautions are subject to risks and uncertainties and are not guarantees of future performance.
What Was Disclosed
New Era Energy & Digital, Inc. disclosed two agreements entered into on September 18, 2026: a 20-year Power Purchase Agreement for up to 207 MW of electricity for its Texas data center project, and a Development Framework Agreement granting Vistra equity and preferential rights at the project site.