TeraWulf Inc. filed a Form 8-K with the SEC on October 5, 2026, disclosing that its wholly-owned subsidiary entered into amended and restated power agreements with Kentucky Power Company to increase contracted capacity at its Muskie Data Campus in eastern Kentucky from 500 megawatts to 1 gigawatt, while also accelerating the timeline for the second 500 MW phase.

Key Highlights

  • Capacity doubled: The Amended & Restated KY Power Agreements increase Muskie's contracted power capacity from 500 MW to 1 GW.
  • Accelerated timeline: The planned delivery of Muskie's second 500 MW phase was moved from 2030 to 2029, subject to Kentucky Public Service Commission approval and Kentucky Power's construction schedule.
  • First phase on track: The first 500 MW phase at Muskie remains targeted to begin ramping in 2028, according to the filing.
  • Agreements executed: The Amended & Restated KY Power Agreements were executed on October 1, 2026.
  • Financing plans: The company disclosed it intends to increase its existing senior secured revolving credit facility and seek additional senior secured debt to support letter of credit needs tied to long-term power development partnerships.
  • No assurance of financing: The filing states "there can be no assurance that the Company will obtain any additional financing."

TeraWulf's Muskie Campus Power Agreements Amended to Double Capacity

According to the filing, TeraWulf's wholly-owned subsidiary, DB Long Hunts Data LLC, entered into the Amended & Restated KY Power Agreements with Kentucky Power Company, described as an American Electric Power company. The agreements cover transmission infrastructure and energy services at Muskie Data Campus, located in eastern Kentucky. The filing reports that the agreements were executed on October 1, 2026, and the press release announcing the development was issued on October 5, 2026. TeraWulf's common stock trades on NASDAQ:WULF.

The filing discloses that the revised agreements raise Muskie's total contracted power capacity from 500 MW to 1 GW. The second 500 MW phase is now targeted for delivery in 2029 rather than 2030, though the filing notes this acceleration is "subject to Kentucky Public Service Commission approval and Kentucky Power's construction schedule." The first 500 MW phase remains targeted to begin ramping in 2028, as stated in the disclosure.

Separately, the filing addresses TeraWulf's financing strategy in connection with its data center campus development. The company indicated it intends to upsize its existing senior secured revolving credit facility and to seek additional senior secured debt, with the stated purpose of supporting letter of credit needs related to long-term power development partnerships with utilities. The filing specifies that the revolving credit facility upsize "will be subject to customary closing conditions." The filing contains forward-looking statements, which TeraWulf identifies as subject to risks, uncertainties, and assumptions described in the cautionary language included in the report.

What Was Disclosed

TeraWulf disclosed amended power agreements doubling Muskie's contracted capacity to 1 GW, an accelerated second-phase delivery target of 2029, and plans to increase its senior secured revolving credit facility and raise additional senior secured debt.