Key Highlights
- Updated Thacker Pass Phase 1 Capital estimate stands at USD 3.83 billion, including contingency.
- The company held cash of USD 961.6 million and restricted cash of USD 297.1 million.
- DOE Loan advances total USD 1.448 billion through September 30, 2026.
- A USD 53.6 million gain on the JV Warrant was recognized in the quarter.
Lithium Americas (NYSE:LAC) reported a third-quarter 2026 loss per share of USD 0.05, against an estimate of a loss of USD 0.03. The company is a development-stage lithium Business and has no revenue; its main asset is the Thacker Pass project in Nevada, which it manages.
At September 30, 2026, Lithium Americas owned a 62% interest in Thacker Pass, with General Motors holding 38%. The U.S. Department of Energy holds a warrant to purchase non-voting units of the joint venture, equal to a 5% economic interest on January 30, 2026, at an exercise price of USD 0.0001 per unit.
Updated Capital Estimate and Construction Timeline
The company completed an updated capital estimate for Thacker Pass Phase 1 of USD 3.83 billion, including contingency, against the prior estimate of USD 2.93 billion. The update reflects advanced construction, detailed engineering and procurement, and external factors that arose after the final Investment decision in April 2025.
The filing itemizes the drivers. Tariffs and logistics total about USD 100 million, with Tariff exposure now put at about USD 60 million, down from a prior USD 80 million to USD 100 million range, because most equipment and materials have been received. Craft labor wage rates and compensation Inflation account for about USD 150 million, labor install rates for piping, steel and equipment about USD 245 million, and engineering, procurement and construction management and contractor staffing about USD 100 million.
The company continues major construction at Thacker Pass Phase 1, targeting mechanical completion in late 2027, with ramp-up through 2028.
Liquidity, Loan Advances and Fair Value Items
At September 30, 2026, the company had cash of USD 961.6 million, compared with USD 568.2 million at December 31, 2025, restricted cash of USD 297.1 million, against USD 337.4 million, and non-GAAP Working Capital of USD 986.4 million, against USD 734.8 million.
The Department of Energy loan advances were USD 435.0 million on October 20, 2025, USD 432.0 million on February 24, 2026, USD 342.0 million on June 3, 2026 and USD 239.0 million on August 21, 2026, totaling USD 1.448 billion through September 30, 2026.
A gain on the change in fair value of the JV warrant, including obligations under the put, call and exchange agreement, was USD 53.6 million for the third quarter and USD 63.5 million year to date, mainly reflecting the decline in the share price from USD 3.85 on June 30, 2026 to USD 2.63 on September 30, 2026. Transaction Costs were USD 8.3 million year to date, against USD 18.3 million. Interest costs on the convertible Debt are capitalized as part of the Thacker Pass construction in progress balance while Capitalization criteria are met.
Capital Estimate Components to Reference
The reported estimate increase is broken into named components: tariff and logistics, craft labor wage rates, labor install rates and contractor staffing. The loan advance schedule, the three-way ownership split among the company, General Motors and the Department of Energy warrant, and the cash and working capital balances are the other disclosed items for the period.