Key Highlights

  • Ongoing EPS of USD 1.52 rose from USD 1.24 a year earlier and topped the consensus estimate of USD 1.39.
  • Revenue of USD 4.17 billion rose 7% but landed below the consensus estimate of USD 4.26 billion.
  • GAAP Net Income of USD 960 million compared with USD 524 million, as GAAP diluted EPS rose to USD 1.52.
  • The five year Capital plan totals USD 70 billion, and initial 2027 ongoing EPS guidance is USD 4.48 to 4.62.

Xcel Energy Inc. (NASDAQ:XEL) reported third quarter 2026 ongoing Earnings of USD 1.52 per share, above a consensus estimate of USD 1.39 and up from USD 1.24 in the same quarter of 2025. Total operating revenues were USD 4.17 billion against USD 3.92 billion a year earlier, which was below a consensus estimate of USD 4.26 billion. Ongoing EPS is a non-GAAP measure, and the company also reported GAAP diluted EPS of USD 1.52 for the quarter, compared with USD 0.88 a year earlier.

Operating income climbed to USD 1.19 billion from USD 749 million, and the prior year quarter carried USD 287 million of Marshall Wildfire litigation expense compared with USD 1 million this time.

What Moved Earnings Per Share Year Over Year

The company's chief financial officer attributed a USD 0.32 per share gain to higher electric revenues, citing riders, regulatory outcomes and weather. Higher allowance for funds used during construction added USD 0.11, and other items added USD 0.16. Those gains were partly offset by higher interest expense of USD 0.13, common Equity Financing of USD 0.10 and operations and maintenance expense of USD 0.08.

On a weather-adjusted basis, year to date electric sales grew 2.5%. Capital invested reached USD 3.5 billion in the quarter and USD 10 billion year to date, with more than USD 14 billion projected for the full year.

Guidance, Capital Plan and Financing

Chairman, President and Chief Executive Officer Bob Frenzel said the company narrowed its 2026 ongoing EPS guidance to USD 4.10 to 4.16 and initiated 2027 guidance of USD 4.48 to 4.62. The updated 2027 to 2031 capital plan of USD 70 billion includes more than 9 GW of renewables, 3 GW of gas generation and 2 GW of storage. The plan extends annualized rate base growth of about 11% through 2031 and does not depend on signing new Data Center customers. Management also cited more than USD 10 billion of incremental opportunities, including infrastructure for 4 GW of additional data center load.

Funding for the plan includes about USD 26 billion of Debt and USD 8 billion of equity, and more than 40% of the equity need is already contracted. The company targets average EPS growth above 9% through 2031 and above 10% for 2027 to 2030. At September 30, long-term debt stood at USD 36.54 billion against USD 31.83 billion at year end 2025, while cash and cash equivalents were USD 2.48 billion.

Dated Items to Follow Into 2027

Several regulatory and commercial milestones carry specific dates. In Minnesota, a proposed Rate Stabilization Plan would hold electric base rates flat in 2027 and 2028, and a commission decision has been requested in January 2027. A recommendation filing on the 4,100 MW Upper Midwest renewable and storage request for proposals is slated for the coming months, and Colorado generation bids for the Phase II Just Transition request are due in December, with a decision targeted for mid 2027.

On the Demand side, management is targeting electric service agreements for an additional 1 GW of data centers by the end of 2026 and another 3 GW by the end of 2027. The narrowed 2026 ongoing EPS range stands at USD 4.10 to 4.16, against USD 3.37 earned through nine months.