Key Highlights
- A consortium's plans to drill for oil in Greenland's Jameson Land Basin have been delayed due to the need for proper permits and regulatory approvals
- Greenland Energy said drilling would now be delayed until winter 2027 due to the project's complexity, with its shares falling by a third following the announcement
- Greenland's government issued a strong warning after reports that equipment worth $60 million had been moved to the island without proper authorization
- An early geological estimate put contained oil at 13 billion barrels, though the geologists who produced the figure called it highly speculative
Drilling Plans Face Delays Over Permitting Requirements
A consortium developing what it has described as a large Greenland oil prospect has seen its drilling plans delayed after the territory's government said the companies involved had no right to drill in the Arctic region without proper approval. UK exploration company 80 Mile said its plans for the Jameson Land Basin now face delays because of the need for proper permits and regulatory approvals, adding that it remains fully committed to advancing the project despite the disappointing timing impact.
80 Mile, primarily a Mining company, has signed a farm-out agreement with US-listed Greenland Energy that would see 70% of the asset handed to the American explorer in exchange for drilling two oil wells. Greenland stopped issuing new oil licenses in 2021 on environmental grounds, though 80 Mile holds historical exploration rights for the Jameson area from before that policy took effect.
Government Issues Warning Over Unapproved Equipment
At the end of July, Greenland's government issued a strong warning to 80 Mile and Greenland Energy after reports emerged that the companies had moved $60 million worth of equipment to the island, stating that all future logistical matters must be advised and approved by the mineral resources authority before being carried out. On Tuesday, Greenland Energy said its efforts to drill would be delayed until winter 2027 due to the project's complexity, with its shares falling by a third on Wednesday in response.
Greenland Energy, which has not previously operated in any other oil region, is seeking to develop the project on Greenland's east coast, describing it as one of the largest underexplored conventional hydrocarbon basins in the western world. An early estimate put the contained oil at 13 billion barrels, though the geologists who produced that figure called it highly speculative. More than a decade ago, another company spent an estimated $1 billion searching for oil in the region and left without finding commercially viable reserves.
Partners Deny Unauthorized Equipment Transfers
A Canadian drilling partner of Greenland Energy denied claims that it had sent equipment to the remote site, following widespread condemnation from environmentalists and Greenland residents, saying it would not land a drilling rig in Greenland unless the project receives all required regulatory consents from Greenlandic authorities. Greenland Energy said it remains committed to advancing its oil exploration program responsibly and in full compliance with Greenlandic authorities. Greenlandic officials said the project is relatively small but has received disproportionate attention due to some of the rhetoric and personalities involved.