Key Highlights

  • SpaceX disclosed plans to build a Natural Gas power plant in Grimes County, Texas, to power a new $16.8 billion chip Manufacturing Facility called Terafab
  • SpaceX's Data Center power capacity could grow to between 10 and 15 gigawatts by the end of 2027, which would make it the largest data center operator in the US
  • The company already relies on dozens of gas turbines at data center campuses in Tennessee and Mississippi to power AI Training operations
  • SpaceX's power strategy has enabled Cloud Computing deals with Anthropic, worth $1.25 billion a month, and Google, worth $920 million a month

SpaceX Builds Out Natural Gas Power for AI Expansion

SpaceX has disclosed plans to build a natural gas power plant in Grimes County, Texas, where the company is developing a $16.8 billion, 100 million square foot chip manufacturing facility known as Terafab. The company said it will pair the gas plant with a connection to the local power grid and plans to build large battery arrays to store energy on-site, giving the facility multiple layers of power redundancy.

SpaceX's data center operations already account for a significant share of behind-the-meter power generation nationally, relying on dozens of gas turbines at campuses in Tennessee and Mississippi. On an investor call, the company's chief executive said total power capacity could grow to between 10 and 15 gigawatts by the end of 2027, which would make SpaceX the largest data center operator in the US, surpassing the roughly 13 gigawatts currently held by the current market leader.

Speed to Power Drives the Strategy

Connecting large AI data centers to the traditional power grid can take years, with some projects unable to secure grid connections until the 2030s. A single 1-gigawatt AI data center can consume roughly as much electricity as 1,000 Walmart stores, or an entire city the size of San Francisco, making rapid, large-scale power delivery one of the central bottlenecks facing the AI infrastructure buildout industry-wide.

Natural gas offers the fastest available path to reliable, around-the-clock power, allowing companies to bypass lengthy transmission buildouts that would otherwise delay projects for years. SpaceX's approach, often described as "Bring Your Own Power," has enabled it to bring data centers online in a fraction of the time required for grid-connected projects in markets like Virginia, where similar buildouts have historically taken five years or longer.

The company's original Memphis-area campus, which now receives grid power alongside its on-site turbines, has expanded to include four properties along the Tennessee-Mississippi border. A second, larger campus in the region continues to rely primarily on turbine power as the company adds capacity to meet growing computational demand.

Deals and Industry-Wide Adoption

The strategy has supported major cloud computing agreements, including a deal with Anthropic worth $1.25 billion a month and one with Google worth $920 million a month, underscoring how quickly on-site power generation can translate into commercial partnerships for AI compute capacity. Other companies are adopting similar approaches, with dozens of data centers nationally now operating on-site power generation independent of the grid.

A recent industry survey found that most power sector executives plan to pursue on-site generation for future projects, with the large majority citing natural gas as their preferred fuel source. Separately, other major energy and technology companies have struck their own long-term power agreements tied to natural gas production, signaling that off-grid strategies are becoming a standard feature of the broader AI infrastructure buildout rather than an approach unique to any single company.