Key Highlights
- Construction costs for large US data centers rose 13% year over year, more than twice the global rate.
- The gain this year was about three times the last ten-year average, according to Turner & Townsend.
- Power is a major obstacle for 56% of surveyed experts, with Utility connections typically taking one to two years.
- Power costs range from USD 15.01 per watt in Silicon Valley to USD 10.51 per watt in Dallas.
Demand Outruns Supply
Demand for large-scale data centers in the United States this year, driven by the need for computing power for artificial intelligence, grew well beyond the Supply of powered land and the labor to build these structures. It also pushed timelines and risk for contractors. Costs rose 13% year over year to more than twice the global rate, according to a new report from Turner & Townsend, a global project management company. The gain this year was about three times the last ten-year average.
The report looked at more than 500 live or recently completed projects in 62 global markets. It also included a survey of 400 experts in the global Data Center industry. The figures describe large US data centers specifically.
Why Costs Rose
There was some stabilization in cost Inflation this year, but it was not enough to offset the growth in both Demand and the speed of construction and delivery. The firm's North America data center lead said more aggressive schedules lead contractors and subcontractors to build more risk allowances into their pricing. He cited acceleration allowances, more overtime and labor attraction allowances, and higher fees that contractors charge for taking on the risk of delivering at a faster pace than they traditionally take on.
Those factors, combined with the spike in demand and strain on the supply chain, translate into higher costs, he added.
Power as the Constraint
Power is key to every data center, and 56% of those surveyed globally said it was a major obstacle to delivery. Just over half said utility connections typically take between one and two years, and almost a third reported timeframes of more than two years. Costs for power vary by region, from USD 15.01 per watt in Silicon Valley to USD 10.51 per watt in Dallas, based on a typical 60-megawatt design. That 60-megawatt design is the basis for the regional comparison.
Labor and Capacity
Labor continues to be a significant headwind, as with every type of construction in the United States. Just over one quarter of respondents said their contractor capacity, meaning the ability to manage construction backlogs, was sufficient.
The Spending Picture
Capital expenditure on global data centers is projected to rise from about USD 800 billion this year to USD 1.8 trillion per year by 2050, according to a recent PwC report. The report projects the United States capturing almost half of all global Investment in AI infrastructure, which includes both data centers and chips. One example of the scale is a USD 16 billion data center under construction in Saline, Michigan, developed by Related Digital for Oracle and OpenAI.
The Firm's Outlook on Costs
The firm's North America data center lead said he expects cost increases to moderate somewhat, in the 6% to 10% range in the next year. A lot of the major projects have already started or are starting now, so cost risk has been built into those contracts. He said 2026 brought a large increase in new major projects that have been procured.
The report arrives as policymakers weigh the politics of data center construction. President Donald Trump said Friday that U.S. companies building such facilities abroad face a "tremendous tax," a separate announcement covered elsewhere. The cost report concerns U.S. construction, while the tax announcement concerns facilities built outside the country.