Key Highlights
- Shares rose 19.90% in pre-market trading to $23.26, up from a prior close of $19.40
- Reports confirmed Anthropic as the frontier AI lab behind the company's newly disclosed 20-year Data Center Lease
- Signed a 20-year, 191 megawatt data center lease at Rockdale, with a two-year extension option, worth up to $16.1 billion in total contract value
- First 96 megawatts of phased delivery expected by December 2027, with the full 191 megawatts online by June 2028
- Now has $9.8 billion in contracted data center Revenue across 241 megawatts at Rockdale, when combined with its existing AMD lease
- Average annual revenue of $520 million and average annual non-GAAP EBITDA of $412 million once fully deployed
- Market Capitalization stands at $7.34 billion, with a 52-week range of $11.15 to $30.32
Shares Surge as AI Lab Behind New Lease Is Confirmed
Riot Platforms ( Nasdaq :RIOT) shares were trading at $23.26 in pre-market activity on August 11, 2026, up 19.90% from the prior close of $19.40. The move followed reports confirming that the frontier AI lab behind the company's newly disclosed data center lease at Rockdale is Anthropic, adding a specific, high-profile counterparty to a deal the company had already announced.
The lease itself covers a 20-year term for 191 megawatts of capacity at Rockdale, with a two-year extension option, and carries total contract value of up to $16.1 billion. Phased delivery is set to begin with 96 megawatts online by December 2027, with the full 191 megawatts in service by June 2028.
What Riot Platforms Does
Riot Platforms is a vertically integrated Bitcoin Mining and digital infrastructure company headquartered in Castle Rock, Colorado, with large-scale mining facilities in Rockdale and Navarro counties, Texas, and Paducah, Kentucky. The company operates through two core segments: Bitcoin Mining, in which it deploys ASIC hardware to earn Bitcoin via mining-pool participation and engineering support, and Engineering, which designs, manufactures, and installs custom power distribution equipment and electrical solutions for commercial, government, data center, Utility , and renewable energy clients.
Founded in 2000, Riot pursues a strategy of owning and operating its own power infrastructure to reduce costs and improve efficiency in Bitcoin mining, while its engineering Subsidiary supports broader electrification and infrastructure needs. The company is led by Chief Executive Officer Jason Les.
Combined AI Data Center Contract Value Reaches $9.8 Billion
Combined with the company's existing AMD (NASDAQ:AMD) lease at Rockdale, which covers 50 megawatts with 200 megawatts of potential expansion, Riot now has $9.8 billion in total contracted data center revenue across 241 megawatts at the Rockdale site, with average annual revenue of $520 million and average annual non-GAAP EBITDA of $412 million once fully deployed. Rockdale operates as a single-tenant site under a non-binding letter of intent for full deployment, potentially representing more than $1 billion in annual rent upon full buildout, and company continues development and land procurement in parallel with these leasing arrangements.
The company also has a Corsicana campus with 1 gigawatt of approved power under a non-binding letter of intent with a single tenant for the entire site, potentially representing more than $1 billion in annual rent upon full buildout.
Financing Structure Supports the Buildout
Riot's financing strategy includes a $573 million interim Facility from Morgan Stanley (NYSE:MS) to fund Rockdale AI lab development, with investment-grade backstop financing already finalized. The company also secured a near-final $180 million term Loan for AMD's initial 25 megawatts, expected to close in the third quarter of 2026, generating approximately $90 million in net new capital to be redeployed toward the new lease's Equity requirements, reducing net equity need to a range of $30 million to $280 million against $1.2 billion in Liquidity .
Conclusion
Riot Platforms' pre-market surge reflects investor enthusiasm for a data center leasing strategy that has rapidly scaled to $9.8 billion in contracted revenue at a single site, now with a named, high-profile AI lab counterparty confirmed in the Rockdale lease. The financing structure the company has assembled, combining an interim facility, a near-final term loan, and substantial existing liquidity, suggests the buildout is well capitalized even as the company continues to pursue additional leasing arrangements at its Corsicana campus.
This article is for informational purposes only and does not constitute financial, Investment , or trading advice. Readers should conduct their own research and consult a licensed Financial Advisor before making investment decisions.






Please wait processing your request...