Key Highlights
- Texas regulators last week resumed issuing all permits related to Data Center projects after a pause.
- Approvals include air permits linked to SpaceX's USD 24 billion gas-fired power and computing site.
- The grid operator was weighing more than 474 gigawatts of connection requests as of August.
- Almost half of planned off-grid data center capacity in one analysis is located in Texas.
The pause on new data center permits in Texas has ended, and developers are moving quickly. The state's environmental regulator resumed issuing approvals last week, weeks before a new governor who campaigned for tighter limits is due to take office.
The Texas Commission on Environmental Quality said it had restarted all permits related to data center projects. It acted on a directive from the office of outgoing Republican Governor Greg Abbott.
The directive stated that the Electric Reliability Council of Texas, which runs the state grid, had finished collecting information on how data centers affect local communities. That completion cleared the way for the agency to act.
First Approvals
The commission granted air pollution permits to three developments. One covers the USD 24 billion gas-fired power plant and supercomputing Facility of SpaceX (NASDAQ:SPCX) at Boca Chica, outside Brownsville.
The others cover a CloudBurst power plant near San Marcos and a facility of Atlas Energy Solutions (NYSE:AESI) northeast of Abilene. Each involves on-site generation, which has become central to how developers plan new capacity.
A Race Against January
Developers want approvals before the Legislature convenes in January under Governor-elect Gina Hinojosa, a Democrat. She has pledged to rein in data center construction.
Her proposals include a moratorium on new development, an end to the industry's tax breaks and a greater say for local communities over new facilities. How much of that agenda becomes law depends in part on the Legislature.
Abbott himself had changed tone before the November election. After promoting the industry, he issued recommendations calling for data centers to pay their own way, bring their own water and protect the grid.
The Grid Queue
Permits are only one constraint. In August, the grid operator was considering more than 474 gigawatts of requests to connect.
By September, 204 projects representing 66.4 gigawatts had met the standard for conditional inclusion as base load, a category for projects with the best prospect of being energized on their initial request. Another 158 projects, totaling 127.9 gigawatts, qualified conditionally as studied load and may receive different allocations or wait longer.
The related interconnection study is not scheduled to begin until April 2027, and no completion date has been set, a lawyer familiar with the process said. Many applicants therefore face a long wait for certainty about power.
Building Private Power
Delays have pushed developers toward generating their own electricity. Analysis by Cleanview, which tracks data center development, identified 59 US facilities with about 90 gigawatts of combined capacity that plan to build behind-the-meter power.
Almost half of that capacity is in Texas. Developers there can draw on abundant Permian Basin gas, extensive pipelines and a comparatively light regulatory environment.
Generators in Demand
Large technology companies are also looking beyond gas turbines. ERock (NYSE:EROC), a Houston maker of Natural Gas generators that went public in June, counts Meta (NASDAQ:META), Anthropic (NASDAQ:ANT) and Microsoft (NASDAQ:MSFT) among its data center clients in Texas.
Its equipment also keeps H-E-B grocery stores running during severe weather, a role that gained prominence after the grid failed in Winter Storm Uri in 2021. The company is expanding its Houston factory to work through a contracted Backlog of USD 1.7 billion.
Chief executive John Carrington has said the Business can add 1.2 gigawatts within 12 months for USD 20 million or less. He also indicated that closer scrutiny in Texas could lead developers to consider other states, pointing to interest from Arkansas, Oklahoma and West Virginia.
Uncertainty After the Vote
Investors see a meaningful obstacle without a clear measure of its size. One infrastructure Investment manager said significant regulatory uncertainty now surrounds data center construction, while still believing that planned spending by the largest technology companies would take place, with some of it relocated.
That distinction matters for local economies. A project that moves elsewhere takes its investment, tax base and electricity Demand with it, but also its water use and pressure on the grid.
What January Could Change
The restart gives developers a window whose length depends on lawmakers and the incoming administration. Permits already granted may be treated differently from applications still pending, and any moratorium would need to define which projects it covers. Those details determine whether the current rush secures lasting rights or only a place in a longer queue.
Grid access remains a separate hurdle that new environmental approvals do not remove. Companies that Supply their own power can sidestep part of the wait, although they still need fuel, equipment and community acceptance. Hinojosa's first proposals to the Legislature, and the response of lawmakers from areas with major projects, would show how far the state's welcome to the industry is going to change. Developers elsewhere are watching, since other states are courting the same investment.